OUR WORK – CASE STUDY 1

Building 2
Overview

PROJECT: Complete Renovation of a 3 Bedroom House in Wembly, North West London

Timescale: 8 Weeks

  • Full electrical wiring & plumbing
  • Poor conditions meant all walls had to be rebuilt from timber & fitted with brand new plaster board & skimmed
  • Installations of 1 bathroom
  • Creating a new downstairs WC
  • Installing a new kitchen with the fitting of 2 steel beams to widen the entrance
  • Re-rendering and painting the exterior of the property
  • Fitting engineered wood flooring to the downstairs rooms, tiles to bathrooms and kitchen, and carpet to stairs and bedrooms.
  • 1 week timescale for fitting decking and landscaping the garden.